Exam - IT-Passports

12 downloads 28 Views 363KB Size Report
IT Certification Guaranteed, The Easy Way! 1 / 4. Exam. : C-TSCM42-64. Title. : SAP Certified Application Associate. - Production - Planning. & Manufacturing ...
IT-Passports 専門 IT 認証試験問題集提供者

http://www.it-passports.com 1 年で無料進級することに提供する

IT Certification Guaranteed, The Easy Way!

Exam

: C-TSCM42-64

Title

: SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP4

s: Vendor Vendors

SAP

Version : DEMO

1/4

IT Certification Guaranteed, The Easy Way!

NO.1 Which one of the following scheduling types cannot be assigned as default to an order type (production order)? A. Midpoint B. Forward C. Only capacity requirements D. Backward Answer: A NO.2 In the SAP ECC system, a material is produced with the help of production orders. Though originally used for rate-based planning only, the planning table is to be used to plan this material. On the initial screen of the planning table, you select this material and then receive a message informing you that you cannot use the planning table for this material. Which one of the following reasons for this message applies? A. The series production indicator has not been set. B. There is no valid production version for this material. C. There are no planned orders or production orders present. D. There are no requirements present. Answer: B NO.3 Which of the following activities is necessary for the capacity availability check to be carried out automatically when a production order is released? A. Activate the availability check and assign a checking rule to the work center for the operation to be checked. B. Activate the availability check and assign the check control to the plant. C. Activate the availability check and assign an overall profile in check control for the business function order release. D. Activate the availability check and assign an availability checking group to the material master for the product to be produced. Answer: C NO.4 The company that you advise does not want to manage certain value-intensive materials in the warehouse stock. Instead, the user wishes to control material provision in such a way that these materials are procured directly for the production and/or process order. How can you fulfill this request? (Choose two.) A. Using the special procurement key subcontracting in the material master for the component B. Using the special procurement key direct procurement/external procurement in the material master for the component C. Using the item type non-stock item in the bill of material for the material in question D. Using the procurement type external procurement in the material master for the component E. Controlling the material in question as a co-product Answer: B,C NO.5 Which of the following requirements for a manufacturing plant can be supported by using process 2/4

IT Certification Guaranteed, The Easy Way!

manufacturing? (Choose three.) A. Master recipe-based manufacturing. B. Material requirements planning for production resources. C. Manufacturing without orders. D. Variable calculation of material quantities (product output, material usage). E. Manufacturing in charge quantities. Answer: A,D,E NO.6 The master data for an in-house production process is to be set up in the SAP ECC system. To do this, you should create a suitable routing that plans for five operations in an initial sequence (10,20, 30, 40, 50). There should be an option of relocating operations 30 and 40 to a second sequence on other work centers if there are capacity bottlenecks. What sequence type would you use to create the second sequence in the system? A. Substitute sequence B. Alternative sequence C. Parallel sequence D. Standard sequence Answer: B NO.7 In your company planning strategies are used in the SAP-ECC demand management that are based on consumption. Which of the following statements about consumption is true? (Choose two.) A. A consumption situation is dynamic and is always restructured with the planning run. B. Consumption can also take place between order reservations and planned independent requirements, depending on the strategy. C. Consumption always takes place on the material level between the planned independent requirements and the planned orders. D. The consumption parameters (consumption mode and consumption interval) can be set in the material master or in the MRP group. Answer: B,D NO.8 A customer has been using planning strategies 30 (production by lots) and 10 (anonymous maketo-stock production) in SAP ECC. The customer wishes to move in part to planning strategy 40 (planning with final assembly). The issue of consumption has an effect here for the first time. Which properties apply for consumption with planning strategy 40? (Choose two.) A. Consumption can lead to an increase of the originally planned overall production quantity. B. Consumption can result in the subsequent specification and adjustment of planning elements in terms of quantity and date, by means of customer orders that arrive. C. Consumption can reduce the originally planned production quantity. D. Consumption creates a static and binding assignment, between the planned independent requirements recorded in advance and the customer requirements that arrive, for the entire procurement process. Answer: A,B

3/4

IT Certification Guaranteed, The Easy Way!

NO.9 An enterprise based in the USA produces an end product that is used with the unit of measure"pound" (LB). The material is now to be marketed in the EU. A prerequisite for this is that the material can be sold with the unit kilogram (KG). Which of the following solutions does SAP ECC offer? A. In the basic data customizing, you create a unit of measure group that converts pounds to kilograms. You then assign this to the material master on basic data view 1. B. You create a new material with a reference to the original material and assign the metric unit of measure to the new material master. C. In the material master, you create a conversion factor for converting pounds to kilograms on basic data view 1. D. There is no need to take any action. There is a general conversion in the central customizing of units of measurements, so that automatic conversion of pounds to kilograms takes place. Answer: D NO.10 The user you advise requests that you make it possible for the user to produce materials for stock,for customer orders, projects, orders and cost centers with production orders. Where can you make settings to ensure these options? A. Serial number profile. B. Settlement profile. C. Valuation variant. D. Production scheduling profile. Answer: B

4/4