JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT 2008 14(4): 295–306

VISUALIZING SIMULATED MONOLITHIC CONSTRUCTION PROCESSES Magdalena Hajdasz Dept of Construction Engineering and Management, Poznań University of Technology, Piotrowo 5, 60-965 Poznań, Poland E-mail: [email protected] Received 4 Apr 2008; accepted 19 Nov 2008 Abstract. This paper concerns visualizing simulated construction processes by using two modules, which are part of the expert system. Modelling and analyzing construction processes by using simulation and visualizing results technique allows participants to provide an in-depth insight into this complex undertaking. The system discussed has a hierarchical and modular structure and is designed for monolithic constructions. Major elements of this system are objects such as: concrete mixers, buckets, slip forms, cranes and a building team. The paper describes the work of two modules that enable combining production systems of sets of means, simulation, and visualisation results. Simulation is a valuable tool in analyzing construction process because it allows construction designers to carry out experiments that make evaluation of different variants possible. Visualizations presented offer an insightful approach to understand complexities of the construction process. The dynamic nature of the construction process has been taken into account and is handled by the system. Keywords: construction operations, monolithic construction processes, decision support and expert systems, modelling, simulation and visualisation.

Issues of decision support and expert systems in structural engineering domain were discussed in works of Adeli (1988); Brandon et al. (1988); Durkin (1994); Anderson (1996); Poon et al. (2000, 2003; Poon 2004); Mitkus and Trinkuniene (2006); Kaklauskas et al. (2005, 2007a); Zavadskas et al. (2006); Golabchi (2008). Expert systems development, classification, methodologies and applications from 1995 to 2004 have been discussed by Liao (2005). Recent literature looks on modelling as a design activity and models as complimentary and alternative media, which are often used in research on construction processes (Ayres 2007). The modelling supports a wide range of construction applications and, among other things, design, construction planning, site layout planning, estimating, valuating and maintenance. The notion of modelling has been widely researched (Dawood 1994; Yang et al. 1996; Marlewski and Hajdasz 2000; Aouad et

al. 2006; Ayers 2007). Researchers have broadly addressed the concept of modeling and employed modelling strategies in various domains of construction. For instance, Yang et al. (1996) developed expert systems in construction management; Poon et al. (2000, 2003); Poon (2004) introduced a new approach for modelling the construction process based on the use of an expert system; Zhang et al. (2005) focused on the consideration of break in modelling of construction processes; Doloi and Jaafari (2002a, b) designed a dynamic simulation model for the strategic decision-making. Problems in modelling, simulation and optimal managing of building processes are under investigation in theoretical and practical aspects (Kamat and Martinez 2001, 2005; Doloi and Jaafari 2002a, b; Mohamed and AbouRizk 2005; Changwan et al. 2006). One of the greatest difficulties in developing simulation models is the ability to realistically present the obtained results. Advanced simulation and visualization relating to the production processes have been discussed among others by Karhu (2003), Sampaio et al. (2005), Kamat and Martinez (2005, 2008). Multicriteria decision-making methods have been applied in various aspects of the investment process (Kaklauskas et al. 2007a, b; Mitkus and Trinkuniene 2007; Banaitienė et al. 2008). This area has been explored by Zavadskas et al. (2003), who discussed problems of selection of rational construction variants, also, Zavadskas et al. (2008) presented a new method of multiple criteria complex proportional assessment with values determined in intervals – COPRAS-G; Grierson and Khajehpour (2002) introduced a computerbased method for the multicriteria conceptual design of

JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT http:/www.jcem.vgtu.lt

ISSN 1392-3730 print / ISSN 1822-3605 online DOI: 10.3846/1392-3730.2008.14.29

1. Introduction This paper deals with decision support (DSS) and expert systems (ES) as well as modelling and simulation (M&S) domain. Construction investment process is a long-term and complex activity during which numerous problems occur. Expert systems, simulation and visualization tools as well as multi-criteria optimization methods in many aspects and stages of the investment process have advanced considerably in recent times. 1.1. Literature review

295

296

M. Hajdasz. Visualizing simulated monolithic construction processes

high-rise office buildings; Hajdasz and Marlewski (1999) developed a multicriteria analysis of the construction process. The author of this paper has continued research on monolithic constructions and linked the study of expert systems and modelling with simulation and visualization of the results obtained. The use of virtual reality techniques and new perspectives to teaching subjects related to the field of civil construction are widely discussed in works of Marlewski and Hajdasz (2000) and Sampaio et al. (2005). The extensive critical review of the construction process models has been discussed by Poon et al. (2003). 1.2. The aim of research The system presented belongs to a group of tools which provide a new quality in designing construction process by introducing simulation of modelled processes. The author has employed in this article a slightly different approach to discuss issues concerning visualization techniques in construction. In this approach a strong emphasis has been put on the visualization and descriptive analysis of phenomena taking place in construction processes rather than on their realistic description. Therefore, the aim of this research is not to create a realistic 3D animation, but to provide a thorough analysis in which visualizations are helpful in understanding the whole process. This paper on the one hand reveals the work of the expert system designed and, on the other, it presents analytical capabilities of the selected modules. The working of the two modules concerns: process simulation (SiCE) and combination of co-operating machines and groups of workers (CoCE) and visualization of the results obtained in the process of working of these modules. The modules are: Simulation of Co-operating Elements (SiCE) and Combination of Co-operating Elements (CoCE). The visualization qualities of the SiCE and CoCE modules will be discussed in particular. In order to highlight these qualities a picture of the working of the acceptance of crane module has been included in the discussion. The expert system presented is concerned with technology designing and monolithic processes organization and is controlled by decision-maker’s preferences revealed during a dialogue session. This paper discusses a selected issue of a complex cyclic process which is the efficiency change of the production set, when the construction rises. When the height of the object changes, it affects the conditions of the realization of the project, which may require modifications of decision maker’s preliminary assumptions, if the initial result is to be achieved. This process is of a dynamic nature which is identified and handled by specific modules.

constructional tasks, the knowledge base consists of a set of facts or object definitions and a set of rules. These rules contain knowledge about correct or ideal solutions as well as knowledge on how to control the construction process. Due to the specific character of the domain, 2 kinds of rules have been distinguished: micro rules, which describe the technological and organizational processes, and macro rules, which control the design process. Modules (SiCE) and (CoCE) exemplify micro rules activities. The considered expert system architecture is presented in Fig. 1. The following scheme presents a relationship hierarchy of the system elements. Fig. 1 also contains modules not discussed in this paper. DATA BASE CONRETE MIXER CRANES

OTHER OBJECTS

SLIP FORM

CONCRETE PLACERS

SILO

BUCKETS

STEEL FIXERS PLASTERERS

KNOWLEDGE BASE

MICRO RULES

MACRO RULES

TECHNOLOGICAL AND ORGANIZATIONAL RULES

DESIGN RULES

TECHNOLOGICAL AND ORGANIZATIONAL SCHEMES

PRODUCTION UNIT EFFICIENCY

PROCEDURE RULES INFERENCE MECHANISM USER’S INTERFACE

VARIOUS UNITS

USER

TIME CONTROL

DOCUMENTATION

1.3. Expert system and modules The expert system designed for this research consists of data base, knowledge base, inference mechanism and includes a number of units (modules), such as the procedure for accepting a crane, a module analyzing the work of building gangs, unit arranging a set of objects, scheduling module and a unit, providing the multi-criterion analysis. In this system, as in most expert systems for

SIMULATION MODULE SiCE ACCEPTANCE OF CRANE

GRAPHIC SCHEDULE

MULITCRITERIA ANALYSIS

ARRANGE-MENT OF SET OF OBJECTS CoCE

ANALYSIS OF TEAM WORK

Fig. 1. Expert system architecture

297

Journal of Civil Engineering and Management, 2008, 14(4): 295–306

The solutions suggested are universal and applicable to monolithic constructions. Problems presented in the article are discussed on the basis of the example of silos constructed using slip forms. The modules described can work on a stand-alone basis, independently of an expert system. It should be emphasised that the article focuses on presentation of behaviour of processes modelled and on revealing any relations between elements, and not on an analysis of particular data. The prototype of this expert system and working of selected modules have been further developed by Hajdasz and Marlewski (1998, 1999) and Marlewski, Hajdasz (2000). This system is constantly under investigation as a generalization of the system for the monolithic construction, and is yet to be designed (initially the prototype has been developed for the purpose of the silos construction which has been thoroughly researched by Hajdasz (1998)). 2. A conceptual model of construction process The complexity and flexibility of the construction process leads to many difficulties in modelling production systems. One of the most important and difficult tasks in creating expert systems are acquisition and representation of the natural knowledge and modelling construction processes. The article is concerned with cyclic monolithic processes by an example of silos building. Before a model of construction process was made, sub-processes had been created. Then detailed observations, measurements, and analysis of particular sub-processes were carried out. Many sub-models were designed and then they were synthesized to a model of the complex construction process. An expert system was created for this complex process. To illustrate different modelling stages 2 sche-

mes are shown. The first one (Fig. 2) reveals cyclical complex construction process; the second (Fig. 3) shows a submodel as a sequence of repeated activities. The cyclic character of this process is fleshed out in Fig. 2. Major elements of this production system are objects, such as concrete mixers, buckets, slip form, cranes and building team. The construction process involves a complex interaction between equipment, crews and materials. A strict technological regime demands all these cooperating elements to be well harmonized. The model is of a universal character for monolithic constructions. After values are added, the model has an individual character. The designer's problem concerns arranging such resources that make possible the erection of silo walls at determined rate. This requires taking into account the following factors: the concrete casting time, external conditions and the dynamic character of the erection process (the object grows as time goes by). The aim can be achieved by the use of machines, various in type and number, and combining different working gangs. Submodels with their boundaries and interactions are taken into consideration, which allows presenting essential details. The examples presented below concern a part of the complex process marked with a double line in Fig. 2. All components marked comprise a series of sequentially repeated operations, which have been presented on a network diagram of the model discussed (Fig. 3). Submodel presents sequential and repetitious activities. The operation cycle is repeated. However, according to the specifics of the construction process, these repeating cycles are realized at a different pace, since activities are taking place in different points (in this case at different height).

EXTERNAL CONDITIONS

CONCRETE PLACERS

CRANE

TRANSPORT BUCKET

SLIP FORM

PLASTERERS

OTHER OBJECTS CONCRETE MIXER

Fig. 2. A conceptual model of complexity cyclical process

STEEL FIXERS

298

M. Hajdasz. Visualizing simulated monolithic construction processes

INFORMATION: TASK, STATE, RESOURCE,

NETWORK MODEL

ACTIVITY, TIME DURATION FOLLOWING PROCESSES

TRANSPORT OF THE CONCRETE MIX PRODUCTION OF THE CONCRETE MIX

PUTTING THE CONCRETE MIX INTO THE BUILDING CONSTRUCTION

PRECEDING PROCESSES

CONSIDERING A SINGLE CYCLE

Fig. 3. Submodel presenting chronological sequence of construction operations is shown on the network diagram

Therefore, each current activity is similar, but not the same. It described the behaviour of the processing elements (crews, equipments) and activities (proceeding, temporary, following). This paper discusses cases, in which harmonisation of all elements of a system is the key criterion (economic aspects are not taken into consideration). In the first case, a simulation of work of a system comprising one crane, appropriate number of concrete mixers, concrete buckets, and a group of concreters has been presented. Analytical and visualization capabilities of SiCE module have been presented in detail. The other example analyses a CoCE module capable of combining sets of a different number of cranes and an appropriate amount of concrete mixers, concrete buckets and concreters in such a way that an uninterrupted work of all components can be ensured. In both cases, a dynamic character of the process has been taken into account. 3. Simulation and process visualization Simulation is a valuable tool that is well situated to the analysis of construction process because it allows construction designers and analyst to conduct experiments, which enable evaluation of different variants during planning the construction process phases. The SiCE module is used to visualize several actual construction processes which are tested according to decision-maker’s preferences presented during a dialogue session. Many variations of sets of production means for process realization can be generated. Fig. 4 presents a monitor screen illustrating work of SiCe module for the submodel showed in Fig. 3. The following specification is assumed in this submodel: – production: a concrete mixer (there is a previously generated base of types of available concrete mixers, marked as CM),

– transport: a crane and a bucket (there is a previously generated base of types of cranes and buckets, which may work on a building site, marked as TB), – putting into: concrete placers (4 types of operations are distinguished: the receipt of the concrete mixture from a bucket, the spreading and levelling, the vibrating, marked as CP). Visualization of planned construction operation allows the user to easily and clearly comprehend the dynamic and interrelated behavior of the modelled process after each simulation run. The SiCE module allows for dynamic visualisation of a process that is displayed in a constant mode or interrupted mode, where all following actions start after pressing a button. A simulation of co-operation of main elements (a concrete mixer, crane transporting bucket and concrete placers) has been presented. A screen displays 3 types of information: • A dynamic visualisation of progress in construction building and cooperation among elements of a system (left-hand side of a screen, Fig. 4.1). • A report of production means usage (right-hand side of a screen, Fig. 4.2). • A linear diagram describing changes in work cycles of system elements (bottom side, Fig. 4.3). Fig. 4.4 and 4.5 display pictures taken during the process. The comparison of the 2 pictures (Figs 4.1 and 4.4) reveals that thanks to visualization the process description and its analysis is much more comprehensive than we could observe by employing traditional media. The operation of the SiCE module has to be preceded by a proper selection of cranes, which are to carry out the task. The procedures of selecting the crane have been discussed for the prototype of the system by Hajdasz and Marlewski (1998), Marlewski and Hajdasz (2000), which concerned a non-standard use of a CAS (computer

299

Journal of Civil Engineering and Management, 2008, 14(4): 295–306

1. PROCESS VISUALISATION

2. RESULT FILES

5. LAYERS

4. THE REALIZATION PROCESS

3. LINEAR OCCUPANCY DIAGRAM

Fig. 4. Full screen produced by the program SiCE (simulation captured at stroke number 669) and pictures concern an example of the realization process. When a monolithic structure is erected, a strict regime must be followed concerning the thickness of concrete layers and the layer solidation time

1. A SAMPLE DIAGRAM IN PRODUCER’S CATALOGUE

2. THE CRANE CAN REALIZE THE TASK

3. THE CRANE CANNOT REALIZE THE TASK

Fig. 5. The comparison with the traditional designing form (Fig. 5.1) is user friendly visualization of the crane operability and the silhouette of the silo. The final conclusion – the crane can realize the task Fig. 5.2, the crane cannot realize (the object is too high) Fig. 5.3. Along the horizontal axis Ox, the horizontal radius is marked (in meters). Along the vertical axis Oy, the capacity is marked (in kN)

algebra system) applied in this procedure. The issue of a correct selection of cranes has been widely researched and discussed. The expert system for crane selection has been discussed by Warszawski (1990), whereas Lennerts and Kraus (1992) researched ESBE system and KuoLiang, Haas (1996) dealt with COPE system for the optimal use of cranes and Ali et al. (2005) presented em-

ployed a new approach for automated path planning of cooperative crane manipulators using a genetic algorithm. The result of the working of the acceptance of crane module has been shown on Fig. 5. Two cases are shown on the graph presented in this figure. The first concerns the case when the system has accepted the crane, and the other when the system has rejected the crane in a specific case.

300

M. Hajdasz. Visualizing simulated monolithic construction processes

Visualisation of calculations results is displayed in a user friendly format, similar to the form used in traditional designing. 3.1. Dynamic visualisation The SiCE module presents dynamic visualisation of cooperation of main elements of the sub-process described. At the same time, different states of particular elements of a system are presented, as well as changes in work progress. The screen displays, in symbolic time units, that is, “strokes”, how the construction proceeds. The system reports current aspects of all relations among all components, which allows for observation and analysis of all work phases. Three aspects are easily revealed: actions are sequential; they repeat in a technological cycle, some of them are carried out in a parallel manner. The layers, approximately 2 meters high, are created by numerous crane cycles (one layer requires many crane cycles in reality and many strokes in software. The layer is prepared in 24 hours. In order to create such a layer (concerned with the cycle of the movement of the slip form), many cycles of the concrete mixer, crane and working crews are required. The number of cycles and time cycle of each of these elements is different, which can be clearly seen on the pictures presented. Single cycles and layers are marked with different colours. Fig. 6 presents typical phases of a process.

At the same moment, work of 3 main elements of this partial process is being presented. Each of these elements can be in different states: • States for concrete mixers (CM): production of concrete mix, container loading, waiting for a next container. • States for a crane transporting a container (TB): loading a concrete mixture, transporting a loaded container, guiding a container, unloading a container, transporting an empty container. • States for concreters, actions (CP): guiding a container, unloading a container, concrete mixture distribution, vibrating. The following figures illustrate typical stages. 3.2. Linear diagram Bottom part of the screen (Fig. 4) presents a result of work of main elements as a linear diagram. Changing relations among components are visible. Time values on the horizontal axis are expressed in strokes. A cyclical character of the process was illustrated explicitly. All operations repeat in a defined sequence, but they are not always the same. It was shown that as the height of a silo increased, some operations proceeded longer to accomplish, and some took place as long as earlier. In this case, however, work stoppages became longer. Work stoppages are marked with white rectangles. A scheme is

Fig. 6. Dynamic visualization – 6 typical phases of the process

301

Journal of Civil Engineering and Management, 2008, 14(4): 295–306

1

CM TB CP

2 CM TB CP CM TB CP

3 CM TB CP

4

1 cycle

15 cycle

Fig. 7. Linear occupancy diagram describing changes in work cycles of system elements – 4 cases

updated dynamically, if any changes occur. Temporal dependences between presented elements (CM, TB and CP) are different for subsequent stages. In real conditions of realization, such detailed observation and such exact results would be impossible. Linear diagram in Fig. 7 presents results of a simulation for 4 different sets of production systems. In all cases, elements were combined into production systems with the assumption that during the whole process of realization, production means and work groups will remain unchanged. However, each of the cases analyzed had different parameters of machines used and different groups of workers (different number of workers). This module is useful for explaining the results of using different types of equipments and crews for currently being tested production set. Periods of full harmony of all elements as well as any disorders can be observed. Thanks to visualization, it is possible to indicate, when exactly disorders occur. It is easy to notice that on graph 7.4 the first cycle is significantly shorter than the 15th. 3.3. Data collected in results files When the simulation is completed, the report in a form of diagram is displayed (Fig. 8). A report of usage of particular elements in cooperation is displayed on a screen, and values are saved in different files. Results are saved in KOR, KOP, and KOQ files, then the program uses this information, carries out more advanced analyses, and visualizes relations

between elements. Information received concerns, for instance, daily values of efficiency on particular heights of a construction, time needed to accomplish a task, work time usage of all elements of a system in percentages. Temporal dependences between presented elements (CM, TB, CP) are different for subsequent stages (see relations on stage A and B on Fig. 8). Simulation of the examples on Fig. 7 and 8 has been conducted on the basis of the theoretical data in order to reveal a diversity of variants. A tendency of changes can be explained by means of a sub-model in Fig. 9. Fig. 9 presents model of a situation, when for a certain height of a construction, a particular group of workers was selected so that a full harmonization of elements co-operated can be achieved. Since with the increase of the construction, a cycle of work for the crane increases simultaneously, therefore, the number of workers should be decreased in order to avoid unnecessary work stoppages (see Fig. 9b). The assumption of the cases discussed was that during the whole time of construction works a set of elements will remain unchanged. This is why the higher the works are carried out, the lower the efficiency results. The above considerations of 3 elements of the set (concrete mixer, crane and buckets, crew) have been presented on the basis of the working of one crane SiCE module). The working operations and module simulation, when a few cranes are applied, will be discussed below.

302

M. Hajdasz. Visualizing simulated monolithic construction processes

THE COMPARISON OF THE VISUALISED AND CALCULATED FORMS OF THE REPORT THE REPORT CONSIST DATA FROM E2.KOD FILE

A

B

CP

Fig. 8. Percentage of occupancies of absolute engagement of all co-operating elements CM, TB, CP (Oy axis) versus the strokes (Oy axis). Parameters from data file E2.KOD. The comparison of the visualized and calculated forms of the report

STATES FOR CONCRETERS - b1GUIDING AND UNLOADING A CONTAINER - b2CONCRETE MIXTURE DISTRIBUTION (SPREADING AND LEVELLING) - b3 VIBRATING STATES FOR A CRANE: - TRANSPORTING A CONTAINER: - LOADING A CONCRETE MIXTURE - TRANSPORTING A LOADED CONTAINER - GUIDING A CONTAINER - UNLOADING A CONTAINER - TRANSPORTING AN EMPTY CONTAINER

STATES FOR CONCRETE MIXERS:

- PRODUCTION OF CONCRETE MIX - CONTAINER LOADING - WAITING FOR A NEXT CONTAINER

DAILY EFFICIENCY ( LAYER)

Fig. 9. A sub-model illustrating changes between particular elements of a system, when the height of a construction increases: b1 – guiding and unloading a container, b2 – concrete mixture distribution (the spreading and levelling), b3 – vibrating. Submodel shows the working of the concrete placers. Time has been marked on the Ox axis. The blue line shows changes of the length of the crane cycle

303

Journal of Civil Engineering and Management, 2008, 14(4): 295–306

4. Combination of co-operating machines and groups of workers The CoCE module allows for combining machines and groups of workers into production sets on a basis of decision-maker’s preferences. By using information saved in the system, the module generates appropriate sets and simulates behaviour of sets created. A particular procedure defines a number of cranes, concrete mixers, and workers needed to have a fully harmonized production set. The relations are unique, but not simple, as shown in Fig. 10. Fig. 10 presents the visualization of results, i.e. the change of number of elements (concrete mixers, cranes, buckets) for subsequent stages of the construction process, when the constant level of efficiency is required. Fig. 10.1 presents a set combined in accordance with the following assumptions: work of leading and auxiliary production means and work groups must be uninterrupted. In order to meet the requirements, at a height of 33.2 m to 89.4 m, a second crane had to be used. Above this height, 3 cranes had to be used (Fig. 10.1). Fig. 10.2 illustrates the action of the module, when one crane is applied. The CoCE module generates numerous solutions (sets of machines and gangs) ensuring a continuous work of several elements. Thanks to this, the situation can be constantly monitored at various stages and compared to more or less advantageous variants. In order to reveal analytical capabilities of the system, screen printouts for 3 different cases are presented in Fig. 11. An influence of a change in a number of cranes (a crane is a leading machine) on efficiency of a production system are observed. The task is to combine elements in such a way that the greatest harmonization possible is achieved. There are cases where the cooperation of elements is a crucial moment affecting the result (economical aspects are not taken into account). Fig. 11.2 presents a model meeting the requirements; an uninterrupted work of all elements is observed. In this case, a second and third crane had to be used. In the first case (Fig. 11.1) it was clear that NUMBER OF CRANES NUMBER OF CONCRETE MIXTURES NUMBER OF BUCKETS

1. CoCE MODULE - 1, 2, 3 CRANES

Fig. 10. An example of simulation of different sets of elements

only one crane caused long work stoppages in concreters’ work. The third case illustrates a situation, in which 3 cranes work together from the beginning. Dark blocks show a loss of working time due to too many cranes used. All examples discussed were presented on a basis of theoretical values. However, they sufficiently illustrate tendencies and precisely show working of the inference mechanism for the CoCE module. Rectangles on the lefthand side of a screen show a change in time of a system cycle. Fig. 11 visualizes several variants of the production sets and considers changes taking place during the realization process. It is worth emphasizing that this visualized user friendly formula is reflected by the module presented in Fig. 9. 5. Conclusions To sum up issues discussed in this article some conclusions can be made pertaining to research findings of a particular case, and some broader implications can be formulated in reference to modelling, simulation and visualization of the construction and expert system. This article discussed the work of the modules SiCe and CoCE as a particular case. The research was to explore the influence of changing conditions on the efficiency of the production cycle. The analysis has been conducted for the silos construction by the monolithic technology. This article discussed the working of the modules SiCe and CoCE in a particular case. The aim of the research was to explore the influence of the changing conditions on the efficiency of the production cycle. The analysis has been conducted for the silos construction in the monolithic technology. The working of the module SiCe has revealed that by employing the same production resources, when the construction raises, the efficiency gradually decreases. The working of the CoCE module has shown how this obstacle can be eliminated. A correct number of machines has been introduced into the construction process (in this case the number has been increased) in order to secure a constant level of efficiency. As a result, a harmonization of all machines and working CYCLE TIME [min]: ONE CRANE SET OF CRANES

2. CoCE MODULE - 1 CRANE

304

M. Hajdasz. Visualizing simulated monolithic construction processes

1. ONLY ONE CRANE

3. THREE CRANES WORK TOGETHER FROM THE BEGINNING

Height a single crane = set of cranes = a loss = a single crane = set of cranes = a loss = a single crane = set of cranes = loss = a single crane = set of cranes = a loss =

25 m: 1 crane 50 m: 2 cranes 75 m: 2 cranes 100m: 3 cranes

2. AN UNINTERRUPTED WORK OF ALL ELEMENTS - A SECOND AND THIRD CRANE HAD TO BE USED

Fig. 11. An example of simulation of different sets of elements

sets has been obtained. A capability of carrying out work simulations designed in accordance with particular criteria reveals indiscernible in practice the correlation between all elements. Advantages and benefits achieved by employing simulation and visualizations techniques provide an indepth insight into complex construction processes. The simulation and calculations improve construction process planning by organizing the resources for maximum productivity and prepare well-harmonized production sets. This computational analysis demonstrates that by employing improved analytical tools the construction processes can be considered in a way which could not be achieved by means of traditional methods. Visualization of simulation results makes it easier to understand the complexities of construction processes by taking into account their dynamic character. Visualisation of the results obtained also facilitates communication between all participants of the undertaking. In addition, a significant advantage is achieved by obtaining reports concerning each element in every phase of the process. Furthermore, presented visualization modules can be used as very effective tools for educational training in construction process design thanks to their user friendly formula. Developing a satisfying model of the process requires a detailed analysis and a very precise description of the phenomenon. Creating models and then software result is enriching the knowledge of the domain, since new facts and relations are revealed, which are indiscernible by traditional design tools.

Modules of the presented expert system illustrate that this is a modern device for technology designing and work organization. The modelling, simulation and computational analyses demonstrate a great value of the developed system for the complex cyclic construction processes. The system designs monolithic constructions in many aspects such as: selecting sets of machines, detailed analysis of work carried out by work groups, making schedules, and multi-criterion analysis. This article presented only some capabilities of an expert system, which is still under development. References Adeli, H. 1988. An overview of expert systems in civil engineering, in Adeli, H. (ed.). Expert Systems in Construction and Structural Engineering. Chapman and Hall, New York. Ali, M. S.; Varghese, K. and Babu, N. R. 2005. Collision free path planning of cooperative crane manipulators using genetic algorithm, Journal of Computing in Civil Engineering 19(2): 182–193. Anderson, T. 1996. Knowledge types: Practical approach to guide knowledge engineering in domains of building design, Expert Systems 13(2): 143–149. Aouad, G.; Song, W. and Lee, A. 2006. nDimensional Modeling Technology: Past, Present, and Future, Journal of Computing in Civil Engineering 20(3): 151–153. Ayres, P. 2007. The origin of modeling, The International Journal of Systems and Cybernetics 36(9/10): 1225–1237. Banaitienė, N.; Banaitis, A.; Kaklauskas, A.; Zavadskas, E. K. 2008. Evaluating a building life cycle: a multivariant and

Journal of Civil Engineering and Management, 2008, 14(4): 295–306 multicriteria approach, Omega – International Journal of Management Science 36(3): 429–441. Brandon, P.; Basden, A.; Hamilton, I. and Stockley, J. 1988. The strategic planning of construction projects: application of expert systems to quantity surveying. Quantity Surveyors Division of the Royal Institution of Chartered Surveyors in Collaboration with the University of Salford. Changwan K.; Haas, C. T.; Liapi, K. A. and Caldas, C. H. 2006. Human-assisted obstacle avoidance system using 3d workspace modeling for construction equipment operation, Journal of Computing in Civil Engineering 20(3): 177–186. Dawood, N. N. 1994. Developing a production management modelling approach for precast concrete building products, Construction Management and Economics 12(5): 393–412. Doloi, H. and Jaafari, A. 2002a. Conceptual simulation model for strategic decision evaluation in project management, Journal of Logistics Information Management 15(2): 88– 104. Doloi, H. and Jaafari, A. 2002b. Towards a dynamic simulation model for strategic decision making in life cycle project management, Project Management Journal 33(4): 23–38. Durkin, J. 1994. Expert systems: design and development. Macmillan, New York, NY. Golabchi, M. 2008. A knowledge-based expert system for selection of appropriate structural systems for large spans, Asian Journal of Civil Engineering Building and Housing 9(2): 179–191. Grierson, D. E.; Khajehpour, S. 2002. Method of conceptual design applied to office buildings, Journal of Computing in Civil Engineering 16(2): 83–103. Hajdasz, M. 1998. Rule based knowledge in the system supporting the design of the realization of grain silos erected by the slip method. Doctoral Dissertation, Poznan University of Technology. Hajdasz, M. and Marlewski, A. 1998. Adaptation of standard information on cranes to the requirements of an expert system, Statyba [Civil Engineering] 4(4): 297–303. Hajdasz, M. and Marlewski, A. 1999. Computer-aided searching for the optimal time of a technological process realised with production resources of fixed type, in Novel design and information technology applications for civil and structural engineering (editors: B. Kumar, B. Topping), CIVIL-COMP Press, Oxford, UK (1999), 141–152. Kaklauskas, A.; Zavadskas, E. K.; Andruskevicius, A. 2005. Cooperative integrated support system negotiation and decision support system for real estate, Lecture Notes in Computer Science 3675: 235–242. Springer-Verlag. Kaklauskas, A.; Zavadskas E. K. and Trinkunas, V. 2007a. A multiple criteria decision support on-line system for construction, Engineering Applications of Artificial Intelligence 20(2): 163–175. Kaklauskas, A.; Zavadskas, E. K.; Banaitis, A.; Šatkauskas, G. 2007b. Defining the utility and market value of real estate: a multiple criteria approach, International Journal of Strategic Property Management 11(2): 107–120. Kamat, V. R. and Martinez, J. C. 2001. Visualizing simulated construction operations in 3D, Journal of Computing in Civil Engineering 15(4): 329–337. Kamat, V. R. and Martinez, J. C. 2005. Dynamic 3D visualization of articulated construction equipment, Journal of Computing in Civil Engineering 19(4): 356–368.

305

Kamat, V. R. and Martinez, J. C. 2008. Software mechanisms for extensible and scalable 3D visualization of construction operations, Advances in Engineering Software 39(8): 659–675. Karhu, V. 2003. A view-based approach for construction process modeling computer, Aided Civil and Infrastructure Engineering 18(4): 275–285. Kuo-Liang, L. and Haas, C. T. 1996. An interactive planning environment for critical operations, Journal of Construction Engineering and Management 122(3): 212–222. Lennerts, K. and Kraus, D. 1992. A data base concept for ESBE, Computer Methods in Civil Engineering (CMCE) 2(4): 11–19. Liao, S. 2005. Expert system methodologies and applications – a decade review from 1995 to 2004, Expert Systems with Applications 28: 93–103. Marlewski, A. and Hajdasz, M. 2000. A-CAS Aid to the elaboration of an expert system supporting managing a monolithic construction, Mathematics and Computers in Simulation 51: 483–488. Martinez, J. C. and Ioannou, P. G. 1995. Advantages of the activity-scanning approach in the modeling of complex construction processes, in Winter Simulation Conference, IEEE, New York, NY, 1024–1031. Mitkus, S.; Trinkūnienė, E. 2006. Models of indicator systems of construction contraction agreements, Journal of Civil Engineering and Management 12(4): 327–335. Mitkus, S. and Trinkūnienė, E. 2007. Analysis of criteria system model for construction contract evaluation, Technological and Economic Development of Economy 13(2): 244–252. Mohamed, Y.; AbouRizk, S. M. 2005. Framework for building intelligent simulation models of construction operations, Journal of Computing in Civil Engineering 19(3): 277–291. Poon, J.; Potts, K. and Cooper, P. 2000. CONBPS - An expert system to improve the efficiency of the construction process, in UK National Conference on Objects and Integration for Architecture, Engineering and Construction, March 13–14, 2000: Building Research and Establishment, Wateford, UK, 276–285. Poon, J.; Potts, K. F.; Musgrove, P. 2003, CONBPS – an Expert System to Improve the Efficiency of the Construction Process, RICS Research Papers 4(21). Poon, J. 2004. Development of an expert system modeling the construction process, Journal of Construction Research 5(1): 145–158. Sampaio, A. Z.; Henriques, P. G.; Ferreira, P. S. and Luizi; R. P. 2005. Vizualizing construction processes by means of Virtual 3D Models: Two study cases, in From Proceeding (469) Applied Simulation and Modelling. Warszawski, A. 1990. Expert systems for crane selection, Construction Management and Economics 8(2): 179–190. Yang, J.; Heng, L. and Skitmore, M. 1996. Expert systems in construction management: Is the hype over? in Proceedings incit 96, International Construction Information Technology Conference; 131–136, The Institution of Engineers Australia, 11 National Circuit, Barton, ACT 2600. Zhang, H. and Tam, C. M. 2005. Consideration of break in modeling of construction processes, Engineering, Construction and Architectural Management 12(4): 373–390. Zavadskas, E. K.; Ustinovichius, L. and Peldschus, F. 2003. Development of software for multiple criteria evaluation, Informatica 14(2): 259–272. Zavadskas, E. K.; Kaklauskas, A.; Vainiunas, A.; Dabakiene, R.; Gulbinas, A.; Krutinis, M.; Cyras, P.; Rimkus, L.

306

M. Hajdasz. Visualizing simulated monolithic construction processes 2006. A buildings refurbishment knowledge and devise decision support system, Lecture Notes in Computer Science 4101: 287–294. Springer Verlag.

Zavadskas, E. K.; Kaklauskas, A.; Turskis, Z.; Tamošaitienë, J. 2008. Selection of effective dwelling house walls applying attributes determined in intervals, Journal of Civil Engineering and Management 14(2): 85–93.

SUMODELIUOTO MONOLITINIŲ STATYBŲ PROCESO VIZUALIZAVIMAS M. Hajdasz Santrauka Nagrinėjamas sumodeliuoto statybų proceso vizualizavimas naudojant du modelius, kurie yra ekspertinės sistemos dalis. Statybos procesų modeliavimas ir analizavimas, pasitelkiant modeliavimo ir vizualizavimo rezultatus, leidžia pateikti dalyviams nuodugnų šio sudėtingo sumanymo supratimą. Aptariama ekspertinė sistema turi hierarchinę ir agreguotą struktūrą ir yra sukurta specialiai monolitinėms konstrukcijoms. Pagrindiniai šios sistemos elementai: betono maišyklės, kibirai, klojiniai, kranai ir statybos brigados. Šis straipsnis apibūdina dviejų modulių darbą, kuris leidžia suderinti gamybos sistemos priemonių, modeliavimo ir vizualizavimo rezultatus. Modeliavimas yra naudingas įrankis analizuojant statybos procesus, nes leidžia statybos projektuotojams atlikti eksperimentus, kurių metu įvertinamos įvairių variantų įgyvendinimo galimybės. Vizualizavimu išsamiai paaiškinama, kas yra statybos proceso sudėtingumas. Buvo atsižvelgta į dinaminę statybos proceso prigimtį, ir tai buvo išspręsta naudojant šią sistemą. Reikšminiai žodžiai: statybų operacijos, monolitinių statybų procesai, ekspertinės sistemos, modeliavimas, modeliavimas ir vizualizavimas. Magdalena HAJDASZ. PhD. Dept of Construction Engineering and Management, Poznan University of Technology. The expert system discussed has been developed in corporation with the Institute of Mathematics. Poznan University of Technology. Research interests: organization and modelling of construction processes, multicriteria analysis, expert systems, simulation and visualization.